Decision details

Gateway 2: Contract award approval - South Dock Marina: Lock Gates and Structural Works

Decision Maker: Strategic Director of Environment and Leisure

Decision status: Recommendations Approved (subject to call-in)

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To approve the award of the contract

Decision:

 

That the award of the South Dock Marina: Lock Gates and Structural Works contract to DiveCo Marine Ltd in the sum of £834,947.14 for a period of 8 months commencing on 5 October 2020 be approved..

 

That the allocation of a contingency budget totalling £166,989.43 (20%), which will be held within the capital project budget if the contingency is utilised the total contract value will be £1,001,936.57, be approved.

 

Publication date: 29/06/2020

Date of decision: 29/06/2020

Date comes into force if not called in: 07/07/2020

Call-in deadline date: 06/07/2020

Current call-in Count: 0